COMPLEX42™ – BK2 DATA CENTRE

Victoria, Australia – May/June 2024

Case Study Details

Download full case study here

BRC - BK2 Data Centre Trial May2024

 

PROJECT: Enhanced Drilling Performance with Complex42™

SUBSTRATE : Slightly weathered basalt

PLACE : 598B Geelong Road, Brooklyn, VIC, Australia

DATE : May/June 2024

COMPANY : BK2 Data Centre

DRILL RIG : Soilmec SR105

SUMMARY OF RESULTS

Parameter

Soilmec SR105

Pair 1

Soilmec SR105 (Complex42™)

Pair 1

Soilmec SR105

Pair 2

Soilmec SR105 (Complex42™)

Pair 2

Pile No. (900mm)

52

41

407

395

Total Depth

5300mm

5570mm

16000mm

13040mm

Duration/Hole

144 minutes

116 minutes

258 minutes

163 minutes

Rate of penetration

36.8 mm/min

48 mm/min

62.0 mm/min

80 mm/min

Fuel Consumed/Hole

114.4 Litres

76.92 Litres

177.59 Litres

110.9 Litres

Teeth Consumed

11

0

1

0

Hardfacing Consumed

0.71mm

0.1mm

N/A

N/A

*Data extracted from Soilmec DMS Software.
*Note this includes idle time when not drilling.
*On the second pair, the reference marks wore of the drill and a measurement was not taken.

In this case study, we compare the performance and cost-effectiveness of the Soilmec SR105 drilling rig using conventional methods against the same rig utilising Complex42™. The objective was to highlight the significant savings in fuel consumption, duration per hole, and wear on equipment achieved by using only 3 to 4 litres of Complex42™, per hole.

Methodology

Separate trials in close proximity were conducted using the Soilmec SR105 rig to evaluate the effectiveness of Complex42™. The first trial used conventional drilling methods, while the second trial incorporated Complex42™ at a concentration of 0.8% in a water tank (Furfey). The made-up solution was gravity-fed into the hole whilst drilling. This process was repeated near the end of the pad in less competent ground. Key performance indicators measured included total depth, duration per hole, rate of penetration, fuel consumption per hole, teeth consumed, and hard facing consumed.